Technical Capacity: 700,00 GWh/d Unavailable Capacity: 298,00 GWh/d Available Capacity: 402,00 GWh/d
Due to technical problems
Problem is solved.....100% capacity
Technical Capacity: 700,00 GWh/d Unavailable Capacity: 298,00 GWh/d Available Capacity: 402,00 GWh/d
Due to technical problems
Vendor invited on-site....ETA unknown
Technical Capacity: 700,00 GWh/d Unavailable Capacity: 2975,00 GWh/d Available Capacity: 402,50 GWh/d
Due to technical problems
Due to technical problems
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
High current module defect, and there is no spare on site.
Spare part on site and mounted....estimate 22:00 available
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
High current module defect, and there is no spare on site.
Spare part on site and mounted....estimate 22:00 available
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
High current module defect, and there is no spare on site.
Estimate 12-09 12:00 hr up and running
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
High current module defect, and there is no spare on site.
Estimate 12-09 12:00 hr up and running
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
Due to technical problems, vendor needs to visit
Estimate 12-09 12:00 hr up and running
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
Due to technical problems, vendor needs to visit
Estimate 12-09 10:00 hr up and running
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
Due to technical problems, vendor needs to visit
Estimate 12-09 10:00 hr up and running
Technical Capacity: 6,78 GWh/d Unavailable Capacity: 6,78 GWh/d Available Capacity: 0,00 GWh/d
Due to technical problems
Estimate 12-09 1:00 hr up and running
Technical Capacity: 678,00 GWh/d Unavailable Capacity: 678,00 GWh/d Available Capacity: 0,00 GWh/d
Due to technical problems
Estimate 12-09 1:00 hr up and running
Technical Capacity: 395,76 GWh/d Unavailable Capacity: 255,36 GWh/d Available Capacity: 140,40 GWh/d
Due electrical problems in the 110 kv system two of the three compressors have tripped.
Checks have to be done. Probably ready for injection at 10:00 LET.
Technical Capacity: 395,76 GWh/d Unavailable Capacity: 255,36 GWh/d Available Capacity: 140,40 GWh/d
Due electrical problems in the 110 kv system two of the three compressors have tripped.
Checks have to be done. Probably ready for injection at 10:00 LET.
Technical Capacity: 395,76 GWh/d Unavailable Capacity: 255,36 GWh/d Available Capacity: 140,40 GWh/d
Due electrical problems in the 110 kv system two of the three compressors have tripped.
Checks have to be done. Probably ready for injection at 10:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 125,88 GWh/d Available Capacity: 260,00 GWh/d
Norg experienced a trip in a compression utility system, causing the compressors to stop.
Expected to be available for injection again at 17:00 LET.rnUPDATE : there are 2 compressors available at 16:00 LET
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 125,88 GWh/d Available Capacity: 260,00 GWh/d
Norg experienced a trip in a compression utility system, causing the compressors to stop.
Expected to be available for injection again at 17:00 LET.rnUPDATE : there are 2 compressors available at 16:00 LET
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 385,88 GWh/d Available Capacity: 0,00 GWh/d
Norg experienced a trip in a compression utility system, causing the compressors to stop.
Expected to be available for injection again at 17:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 385,88 GWh/d Available Capacity: 0,00 GWh/d
Norg experienced a trip in a compression utility system, causing the compressors to stop.
Expected to be available for injection again at 23:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 385,88 GWh/d Available Capacity: 0,00 GWh/d
Norg experienced a trip in a compression utility system, causing the compressors to stop.
Expected to be available for injection again at 22:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 385,88 GWh/d Available Capacity: 0,00 GWh/d
Norg experienced a trip in a compression utility system, causing the compressors to stop.
Expected to be available for injection again at 20:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 385,88 GWh/d
Compressor unavailability
Event stop is unknown at the moment.rnUpdate: Problem solved. Compressor is ready for injection at 16:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 125,66 GWh/d Available Capacity: 260,22 GWh/d
Compressor unavailability
Event stop is unknown at the moment.rnUpdate: Problem solved. Compressor is ready for injection at 16:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 125,66 GWh/d Available Capacity: 260,22 GWh/d
Compressor unavailability
Event stop is unknown at the moment.rnUpdate: Problem solved. Compressor is ready for injection at 16:00 LET.
Technical Capacity: 385,88 GWh/d Unavailable Capacity: 125,66 GWh/d Available Capacity: 260,22 GWh/d
Compressor unavailability
Event stop is unknown at the moment.
Technical Capacity: 162,70 GWh/d Unavailable Capacity: 162,70 GWh/d Available Capacity: 0,00 GWh/d
compressor unavailable due to technical problems
Problem solved
Technical Capacity: 162,70 GWh/d Unavailable Capacity: 162,70 GWh/d Available Capacity: 0,00 GWh/d
compressor unavailable due to technical problems
Problem solved
Technical Capacity: 162,70 GWh/d Unavailable Capacity: 162,70 GWh/d Available Capacity: 0,00 GWh/d
compressor unavailable due to technical problems
End time is an estimated time
Technical Capacity: 162,70 GWh/d Unavailable Capacity: 162,70 GWh/d Available Capacity: 0,00 GWh/d
compressor unavailable due to technical problems
End time is an estimated time
Technical Capacity: 162,70 GWh/d Unavailable Capacity: 162,70 GWh/d Available Capacity: 0,00 GWh/d
compressor unavailable due to technical problems
End time is an estimated time
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 219,40 GWh/d Available Capacity: 136,80 GWh/d
Two of the three compressors have trip by powerfail
Compressors are checked and up and running.
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 219,40 GWh/d Available Capacity: 136,80 GWh/d
Two of the three compressors have trip by powerfail
Compressors have to be checked by electrical engineer before the can start again.
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 356,20 GWh/d Available Capacity: 0,00 GWh/d
all the compressors have failed for unknow reasonrnrn
End time is an estimate, systems need a check and reset before startup.rnUpdate: Problem is solved and injection will start at 18:00.
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 356,20 GWh/d Available Capacity: 0,00 GWh/d
all the compressors have failed for unknow reasonrnrn
End time is an estimate, systems need a check and reset before startup.rnUpdate: Problem is solved and injection will start at 18:00.
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 356,20 GWh/d Available Capacity: 0,00 GWh/d
all the compressors have failed for unknow reasonrnrn
End time is an estimate, systems need a check and reset before startup.
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 92,60 GWh/d Available Capacity: 263,60 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 1 compressor is down.rnrn
In the evening the temperature will be low enough to start the compressor. At 20:00hr the compressor is back on line.rnUpdate:at 19:00hr the compressor will be back on line.
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 92,60 GWh/d Available Capacity: 263,60 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 1 compressor is down.rnrn
In the evening the temperature will be low enough to start the compressor. At 20:00hr the compressor is back on line.rnUpdate:at 19:00hr the compressor will be back on line.
Technical Capacity: 356,20 GWh/d Unavailable Capacity: 92,60 GWh/d Available Capacity: 263,60 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 1 compressor is down.rnrn
In the evening the temperature will be low enough to start the compressor. At 20:00hr the compressor is back on line.
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 100,58 GWh/d Available Capacity: 295,20 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we had to stop all the compressors
At 21:00 LET the first compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u).rnAt 23:00 LET the second compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u)rnAt 00:00 LET the second compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u)rnEnd time is an estimate.
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 100,58 GWh/d Available Capacity: 295,20 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we had to stop all the compressors
At 21:00 LET the first compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u).rnAt 23:00 LET the second compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u)rnAt 00:00 LET the second compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u)rnEnd time is an estimate.
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 198,91 GWh/d Available Capacity: 196,87 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we had to stop all the compressors
At 21:00 LET the first compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u).rnAt 23:00 LET the second compressor is ready to start with an injection capacity of 98,33 GWh/d. (4096 MWh/u)rnEnd time is an estimate.
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 297,45 GWh/d Available Capacity: 98,33 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we had to stop all the compressors
At 21:00 LET the first compressor is ready to start with a injection capacity of 98,33 GWh/d. (4096 MWh/u). The other two compressors still have to cool down. End time is an estimate.
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 395,78 GWh/d Available Capacity: 0,00 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we had to stop all the compressors
End time is an estimate
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 179,78 GWh/d Available Capacity: 216,00 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we had to stop one of the compressors
End time is an estimate
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 150,26 GWh/d Available Capacity: 245,52 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high
End time is an estimate
Technical Capacity: 395,78 GWh/d Unavailable Capacity: 111,14 GWh/d Available Capacity: 284,64 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high
End time is an estimate
Technical Capacity: 350,13 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 350,13 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we have to stop the compressor.
GRK-UGS will start at 21:00 LET with 4218MWh/h
Technical Capacity: 350,13 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 350,13 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we have to stop the compressor.
GRK-UGS will start at 21:00 LET with 4218MWh/h
Technical Capacity: 350,13 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 350,13 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high and we have to stop the compressor
End time is an estimate time
Technical Capacity: 435,30 GWh/d Unavailable Capacity: 290,20 GWh/d Available Capacity: 145,10 GWh/d
Deferment due to technical issues on two compressors.
Compressor outage first compressor due to instrumental problem. A problem on the third compressor still persist. Therefore third compressor still under repair. Problem solved.
Technical Capacity: 435,30 GWh/d Unavailable Capacity: 290,20 GWh/d Available Capacity: 145,10 GWh/d
Deferment due to technical issues on two compressors.
Compressor outage first compressor due to instrumental problem. A problem on the third compressor still persist. Therefore third compressor still under repair.
Technical Capacity: 435,30 GWh/d Unavailable Capacity: 290,20 GWh/d Available Capacity: 145,10 GWh/d
Deferment due to technical issues on two compressors.
Compressor outage first compressor due to instrumental problem. A problem on the third compressor still persist. Therefore third compressor still under repair.
Technical Capacity: 435,30 GWh/d Unavailable Capacity: 145,10 GWh/d Available Capacity: 290,20 GWh/d
Deferment due to technical issues on two compressors.
Technical problems with recycle valve is solved. One compressor is reinstalled and on duty. An additional problem still persist. Therefore third compressor still under repair.
Technical Capacity: 435,30 GWh/d Unavailable Capacity: 290,20 GWh/d Available Capacity: 145,10 GWh/d
Deferment due to technical issues on two compressors.
Technical problems with recycle valve needs to be solved.rnDuration of the repair had to be extended to 13:00 due to the complexity of the problem.
Technical Capacity: 435,30 GWh/d Unavailable Capacity: 290,20 GWh/d Available Capacity: 145,10 GWh/d
Deferment due to technical issues on two compressors.
Technical problems with recycle valve needs to be solved.rnDuration of the repair had to be extended to 12:00 due to the complexity of the problem.
Technical Capacity: 435,30 GWh/d Unavailable Capacity: 290,20 GWh/d Available Capacity: 145,10 GWh/d
Deferment due to technical issues on two compressors.
Technical problems with recycle valve needs to be solved.
Technical Capacity: 168,00 GWh/d Unavailable Capacity: 168,00 GWh/d Available Capacity: 0,00 GWh/d
Integrity issue with the discharge header injection compressor.
Problems concerning anti surge control still persist. Help to solve problem has been scaled up. REMIT extended to 2nd of May, 14:00hr LET.
Technical Capacity: 168,00 GWh/d Unavailable Capacity: 168,00 GWh/d Available Capacity: 0,00 GWh/d
Integrity issue with the discharge header injection compressor.
Problems concerning anti surge control still persist. Help to solve problem has been scaled up. REMIT extended to 2nd of May, 14:00hr LET.
Technical Capacity: 168,00 GWh/d Unavailable Capacity: 168,00 GWh/d Available Capacity: 0,00 GWh/d
Integrity issue with the discharge header injection compressor.
Compressor has problems with anti surge control, REMIT extended to 2nd of May 4.00h
Technical Capacity: 168,00 GWh/d Unavailable Capacity: 168,00 GWh/d Available Capacity: 0,00 GWh/d
Integrity issue with the discharge header injection compressor.
Compressor has problems with anti surge control, REMIT extended to 2nd of May 2.00h
Technical Capacity: 168,00 GWh/d Unavailable Capacity: 168,00 GWh/d Available Capacity: 0,00 GWh/d
Integrity issue with the discharge header injection compressor.
Repair will take more time; REMIT extended to 22.00h
Technical Capacity: 168,00 GWh/d Unavailable Capacity: 168,00 GWh/d Available Capacity: 0,00 GWh/d
Integrity issue with the discharge header injection compressor.
Expected to be fixed 1st of May u002721 18:00h.
Technical Capacity: 539,00 GWh/d Unavailable Capacity: 539,00 GWh/d Available Capacity: 0,00 GWh/d
Due to technical issues
Uncertain when prod will be availablernExpected end time is updated :23/04/2021 13:00hrnNew expected end time is updated :24/04/2021 12:00 hr
Technical Capacity: 539,00 GWh/d Unavailable Capacity: 539,00 GWh/d Available Capacity: 0,00 GWh/d
Due to technical issues
Uncertain when prod will be availablernExpected end time is updated :23/04/2021 13:00hrnNew expected end time is updated :24/04/2021 12:00 hr
Technical Capacity: 539,00 GWh/d Unavailable Capacity: 539,00 GWh/d Available Capacity: 0,00 GWh/d
Due to technical issues
Uncertain when prod will be availablernExpected end time is updated :23/04/2021 13:00hrnNew expected end time is updated :26/04/2021 06:00h
Technical Capacity: 539,00 GWh/d Unavailable Capacity: 539,00 GWh/d Available Capacity: 0,00 GWh/d
Due to technical issues
Uncertain when prod will be availablernExpected end time is updated :23/04/2021 13:00h
Technical Capacity: 539,00 GWh/d Unavailable Capacity: 539,00 GWh/d Available Capacity: 0,00 GWh/d
Due to technical issues
Uncertain when prod will be available
Technical Capacity: 504,00 GWh/d Unavailable Capacity: 240,00 GWh/d Available Capacity: 264,00 GWh/d
Technical issues
uncertain when technical problems are solved.
Technical Capacity: 504,00 GWh/d Unavailable Capacity: 240,00 GWh/d Available Capacity: 264,00 GWh/d
Technical issues
uncertain when technical problems are solved.
Technical Capacity: 32,53 GWh/d Unavailable Capacity: 16,04 GWh/d Available Capacity: 16,49 GWh/d
Due to technical intergrity
Issue regarding technical integrity has been resolved.
Technical Capacity: 32,53 GWh/d Unavailable Capacity: 16,04 GWh/d Available Capacity: 16,49 GWh/d
Due to technical intergrity
In the most positive sense, we think it will be resolved by the end of the week.
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 134,67 GWh/d
compressor unavailable due to technical problems
The compressor is available at 16:00 LET
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 134,67 GWh/d
compressor unavailable due to technical problems
The compressor is available at 16:00 LET
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
compressor unavailable due to technical problems
compressor unavailable due to technical problems
Technical Capacity: 358,50 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 358,50 GWh/d
One compressor unavailable due to technical problems
The problems are solved
Technical Capacity: 358,50 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 259,72 GWh/d
One compressor unavailable due to technical problems
uncertain when technical problems are solved.
Technical Capacity: 348,54 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 348,54 GWh/d
The outdoor temperature has dropped enough to start the 3nd compressor again rnrnrn
Outdoor temperature has dropped enough to start up third compressorrn
Technical Capacity: 348,54 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 348,54 GWh/d
The outdoor temperature has dropped enough to start the 3nd compressor again rnrnrn
Outdoor temperature has dropped enough to start up third compressorrn
Technical Capacity: 348,54 GWh/d Unavailable Capacity: 89,63 GWh/d Available Capacity: 258,91 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 1 compressor is down.
When high outdoor temperatures will be low enough to start the compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 316,47 GWh/d
The outdoor temperature has dropped enough to start the 3nd compressor again rn
Outdoor temperature has dropped enough to start up third compressor
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
The outdoor temperature has dropped enough to start the 2nd compressor again rn
Outdoor temperature has dropped enough to start up second compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 222,36 GWh/d Available Capacity: 94,11 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therfor 2 compressors are down. rnrnrn
When high outdoor temperatures will be low enough. The compressor will be started
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 207,75 GWh/d Available Capacity: 108,72 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therfor 2 compressors are downrnrnrn
When high outdoor temperatures will be low enough. The compressor will be started
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
The outdoor temperature has dropped enough to start the 2nd compressor again rnrnrn
Outdoor temperature has dropped enough to start up second compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 182,79 GWh/d Available Capacity: 133,68 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 2 compressors are downrnrnrn
When high outdoor temperatures will be low enough to start the compressor
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
The outdoor temperature has dropped enough to start the 2nd compressor againrnrnrn
Outdoor temperature has dropped enough to start up second compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 182,79 GWh/d Available Capacity: 133,68 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 2 compressors are downrnrnrn
When high outdoor temperatures will be low enough to start the compressor
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
The outdoor temperature has dropped enough to start the 2nd compressor againrnrnrn
At midnight we started the second compressor again
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 182,79 GWh/d Available Capacity: 133,68 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 2 compressors are down.rnrnrn
When high outdoor temperatures will be low enough to start the compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. rnTemperature has dropped, 1 compressor started up again. So from now on, two of the three compressors are running
Outdoor temperature has dropped enough to start up second compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 182,79 GWh/d Available Capacity: 133,68 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 2 compressors are down.
When high outdoor temperatures will be low enough to start the compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 1 compressor is down.
When high outdoor temperatures will be low enough to start the compressor.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 1 compressor is down.
At midnight the temperature will be low enough to start the compressor. At 22:00hr the compressor is back on line.
Technical Capacity: 316,47 GWh/d Unavailable Capacity: 98,78 GWh/d Available Capacity: 217,69 GWh/d
Due to the high outdoor temperature the cooling water temperature is to high. Therefor 1 compressor is down.
At midnight the temperature will be low enough to start the compressor.
Technical Capacity: 12,00 GWh/d Unavailable Capacity: 6,00 GWh/d Available Capacity: 6,00 GWh/d
External powerfailure
100% capacity expected at 07:00 LETrnAt 07:45 LET 100% capacity back after reset.
Technical Capacity: 12,00 GWh/d Unavailable Capacity: 6,00 GWh/d Available Capacity: 6,00 GWh/d
External powerfailure
100% capacity expected at 07:00 LET
Technical Capacity: 134,66 GWh/d Unavailable Capacity: 134,66 GWh/d Available Capacity: 0,00 GWh/d
CCC controler of the compressor K-4101 is defect. rnControler has been repared.
Expected that compressor will be available at wednesday 4th March.
Technical Capacity: 134,66 GWh/d Unavailable Capacity: 134,66 GWh/d Available Capacity: 0,00 GWh/d
CCC controler of the compressor K-4101 is defect.
Expected that compressor will be available at wednesday 4th March.
Technical Capacity: 128,00 GWh/d Unavailable Capacity: 128,00 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
Event stop time is an estimate, installations to be checked and a reset to be performed.
Technical Capacity: 128,00 GWh/d Unavailable Capacity: 128,00 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
Event stop time is an estimate, installations to be checked and a reset to be performed.
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Communication card compressor control changed out
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Communication card compressor control changed out
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup.
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Compressor is running again
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Compressor is running again. rnCompressor will produce at 23:00
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Compressor is running again
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Compressor is running again
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Compressor is running again
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup. Compressor is running again
Technical Capacity: 148,13 GWh/d Unavailable Capacity: 148,13 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
End time is an estimate, systems need a check and reset before startup
Technical Capacity: 150,38 GWh/d Unavailable Capacity: 150,38 GWh/d Available Capacity: 0,00 GWh/d
Compressor problem
Event stop time is an estimate, installations to be checked and a reset to be performed.rnCompressor is running again.
Technical Capacity: 150,38 GWh/d Unavailable Capacity: 150,38 GWh/d Available Capacity: 0,00 GWh/d
Compressor problem
Event stop time is an estimate, installations to be checked and a reset to be performed.
Technical Capacity: 150,00 GWh/d Unavailable Capacity: 150,00 GWh/d Available Capacity: 0,00 GWh/d
A short event in the power grid (power supply) caused a trip of the compressor units
Event stop time is an estimate, installations to be checked and a reset to be performed.
Technical Capacity: 150,00 GWh/d Unavailable Capacity: 150,00 GWh/d Available Capacity: 0,00 GWh/d
A short event in the power grid (power supply) caused a trip of the compressor units
Event stop time is an estimate, installations to be checked and a reset to be performed.
Technical Capacity: 150,00 GWh/d Unavailable Capacity: 150,00 GWh/d Available Capacity: 0,00 GWh/d
A short event in the power grid (power supply) caused a trip of the compressor units
Event stop time is an estimate, installations to be checked and a reset to be performed.
Technical Capacity: 350,00 GWh/d Unavailable Capacity: 350,00 GWh/d Available Capacity: 0,00 GWh/d
A short event in the power grid (power supply) caused a trip of the compressor units
Event stop time is an estimate, installations to be checked and a reset to be performed.
Technical Capacity: 945000000,00 KWh/d Unavailable Capacity: 30000000,00 KWh/d Available Capacity: 915000000,00 KWh/d
A short event in the power grid (power supply) caused a trip of the compressor units
End time is an estimate, systems need a check and reset before startup
Technical Capacity: 945000000,00 KWh/d Unavailable Capacity: 30000000,00 KWh/d Available Capacity: 915000000,00 KWh/d
A short event in the power grid (power supply) caused a trip of the compressor units
End time is an estimate, systems need a check and reset before startup
Technical Capacity: 945000000,00 KWh/d Unavailable Capacity: 555000000,00 KWh/d Available Capacity: 390000000,00 KWh/d
A short event in the power grid (power supply) caused a trip of the compressor units
End time is an estimate, systems need a check and reset before startup
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
Problem solved.
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
investigation
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
investigation
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
compressor has failed for unknow reason
investigation
Technical Capacity: 703,83 GWh/d Unavailable Capacity: 216,51 GWh/d Available Capacity: 487,32 GWh/d
Unavailable due to technical integrity on de Norgron pipeline.
Problem is solved
Technical Capacity: 703,83 GWh/d Unavailable Capacity: 216,51 GWh/d Available Capacity: 487,32 GWh/d
Unavailable due to technical integrity on de Norgron pipeline.
Most likely the problem will be solved by monday 25-02-2019
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
Do to equipment failure
Problem is solved.
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
Do to equipment failure
Problem will be solved most likely before the evening.
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
K-4101 unavailable due technical integrity.
Investigation has started.
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
K-4101 unavailable due technical integrity.
Investigation has started.
Technical Capacity: 134,67 GWh/d Unavailable Capacity: 134,67 GWh/d Available Capacity: 0,00 GWh/d
K-4101 unavailable due technical integrity.
Investigation has started.
Technical Capacity: 154,00 GWh/d Unavailable Capacity: 154,00 GWh/d Available Capacity: 0,00 GWh/d
GRKUGS down due to temperature problems ambient temp to high to run the plant.
If the ambient temperature drops it will be possible to start up again
Technical Capacity: 154,00 GWh/d Unavailable Capacity: 154,00 GWh/d Available Capacity: 0,00 GWh/d
GRKUGS down due to temperature problems ambient temp to high to run the plant.
If the ambient temperature drops it will be possible to start up again
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
Power failure by external party.t
Plant has gone into emergency shut-down.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
Power failure by external party.t
Plant has gone into emergency shut-down.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
Power failure by external party.t
Plant has gone into emergency shut-down.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
GRKUGS down due to temperature problems ambient temp to high to run the plant.t
If the ambient temperature drops it will be possible to start up again.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
GRKUGS down due to temperature problems ambient temp to high to run the plant.t
If the ambient temperature drops it will be possible to start up again.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
GRKUGS down due to temperature problems ambient temp to high to run the plant.t
If the ambient temperature drops it will be possible to start up again.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected heat issues due to outside temperature.t
Expected to be able to start again when environment temperature goes down.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected heat issues due to outside temperature.t
Expected to be able to start again when environment temperature goes down.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected heat issues due to outside temperature.t
Expected to be able to start again when environment temperature goes down.t
Technical Capacity: 157,00 GWh/d Unavailable Capacity: 157,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected heat issues due to outside temperature.t
Expected to be able to start again when environment temperature goes down.t
Technical Capacity: 163,85 GWh/d Unavailable Capacity: 163,85 GWh/d Available Capacity: 0,00 GWh/d
Compressor is down.
Unknown, further investigation.
Technical Capacity: 163,85 GWh/d Unavailable Capacity: 163,85 GWh/d Available Capacity: 0,00 GWh/d
Compressor is down.
Unknown, further investigation.
Technical Capacity: 163,85 GWh/d Unavailable Capacity: 163,85 GWh/d Available Capacity: 0,00 GWh/d
Compressor is down.
Unknown, further investigation.
Technical Capacity: 164,00 GWh/d Unavailable Capacity: 164,00 GWh/d Available Capacity: 0,00 GWh/d
Compressor tripped for unknown reasons.
Mechanic is on his way to the location Grijpskerk. After analyzing the failure we expected to start up around midnight.
Technical Capacity: 164,00 GWh/d Unavailable Capacity: 164,00 GWh/d Available Capacity: 0,00 GWh/d
Compressor tripped for unknown reasons.
Mechanic is on his way to the location Grijpskerk. After analyzing the failure we expected to start up around midnight.
Technical Capacity: 164,00 GWh/d Unavailable Capacity: 164,00 GWh/d Available Capacity: 0,00 GWh/d
Compressor tripped for unknown reasons.
Mechanic is on his way to the location Grijpskerk. After analyzing the failure we expected to start up around midnight.
Technical Capacity: 164,00 GWh/d Unavailable Capacity: 164,00 GWh/d Available Capacity: 0,00 GWh/d
Compressor tripped for unknown reasons.
Mechanic is on his way to the location Grijpskerk. After analyzing the failure we expected to start up around midnight.
Technical Capacity: 172,00 GWh/d Unavailable Capacity: 172,00 GWh/d Available Capacity: 0,00 GWh/d
Compressor has stopped while changing over the lube oil pumps. After cooling down the compressor it has started again.
Pending investigation
Technical Capacity: 172,00 GWh/d Unavailable Capacity: 172,00 GWh/d Available Capacity: 0,00 GWh/d
Compressor has failed for unknown reasons
Pending investigation
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unavailability of the injection now included in updated weekplan 19 (rev 5)
Unavailability of the injection now included in updated weekplan 19 (rev 5)
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Further investigation on issue VSDS system. Expected repair and start-up at end of afternoon on Thursday. During the day one or more test-runs can be performed prior to start-up.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Earlier start-ups unsuccesful and issue indentified to be more complex. Further investigation done and repairs to be performed.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Waiting for availability spare parts and repair on-site.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Waiting for availability spare parts and repair on-site.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Waiting for availability spare parts and repair on-site.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Waiting for availability spare parts and repair on-site.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Expected start-up depending on failure analyses.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Expected start-up depending on failure analyses.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Expected start-up depending on failure analyses.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Expected start-up depending on failure analyses.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Expected start-up depending on failure analyses.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Expected start-up depending on failure analyses.
Technical Capacity: 174,00 GWh/d Unavailable Capacity: 174,00 GWh/d Available Capacity: 0,00 GWh/d
Unexpected trip K4101 ( injection compressor)
Expected start-up depending on failure analyses.
Technical Capacity: 495,00 GWh/d Unavailable Capacity: 180,00 GWh/d Available Capacity: 315,00 GWh/d
An unexpected trip of HIPPS/3 wells is causing a reduced capacity of the UGS Grijpskerk withdrawal
Expected to startup the wells again is not expected before the 5th of March 14.00h(GMT).
Technical Capacity: 495,00 GWh/d Unavailable Capacity: 180,00 GWh/d Available Capacity: 315,00 GWh/d
An unexpected trip of HIPPS/3 wells is causing a reduced capacity of the UGS Grijpskerk withdrawal
Expected to startup the wells again is not expected before the 2nd of March 14.00h(GMT).
Technical Capacity: 495,00 GWh/d Unavailable Capacity: 180,00 GWh/d Available Capacity: 315,00 GWh/d
An unexpected trip of HIPPS/3 wells is causing a reduced capacity of the UGS Grijpskerk withdrawal
Expected to startup the wells again is not expected before the 2nd of March 14.00h(GMT).
Technical Capacity: 495,00 GWh/d Unavailable Capacity: 180,00 GWh/d Available Capacity: 315,00 GWh/d
An unexpected trip of HIPPS/3 wells is causing a reduced capacity of the UGS Grijpskerk withdrawal
Expected to startup the wells again is not expected before the 2nd of March 14.00h(GMT).
Technical Capacity: 495,00 GWh/d Unavailable Capacity: 180,00 GWh/d Available Capacity: 315,00 GWh/d
An unexpected trip of HIPPS/3 wells is causing a reduced capacity of the UGS Grijpskerk withdrawal
Expected to startup the wells again is not expected before tomorrow 10:00hr (GMT).
Technical Capacity: 495,00 GWh/d Unavailable Capacity: 180,00 GWh/d Available Capacity: 315,00 GWh/d
An unexpected trip of 3 wells is causing a reduced capacity of the UGS Grijpskerk withdrawal.
Expected to startup the wells again within the hour. Update: 00:30(GMT) evry thing is up and running.
Technical Capacity: 495,00 GWh/d Unavailable Capacity: 180,00 GWh/d Available Capacity: 315,00 GWh/d
An unexpected trip of 3 wells is causing a reduced capacity of the UGS Grijpskerk withdrawal.
Expected to startup the wells again within the hour. Update: 00:30(GMT) evry thing is up and running.
Technical Capacity: 701,83 GWh/d Unavailable Capacity: 161,96 GWh/d Available Capacity: 539,87 GWh/d
Flow line / manifold blocked in and made pressureless for maintenance (small leakage)on monday.
Monday they will start with reparing the small leakage. Changed in scheduled unavailability.
Technical Capacity: 701,83 GWh/d Unavailable Capacity: 161,96 GWh/d Available Capacity: 539,87 GWh/d
Flow line / manifold blocked in and made pressureless for maintenance (small leakage)on monday.
Monday they will start with reparing the small leakage.
Technical Capacity: 139,49 GWh/d Unavailable Capacity: 139,49 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped for unknown electrical reason
Electrical engineer on his way to the installation.
Technical Capacity: 139,49 GWh/d Unavailable Capacity: 139,49 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped for unknown electrical reason
Electrical engineer on his way to the installation.
Technical Capacity: 139,49 GWh/d Unavailable Capacity: 139,49 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped for unknown electrical reason
Electrical engineer on his way to the installation.
Technical Capacity: 139,49 GWh/d Unavailable Capacity: 139,49 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped for unknown electrical reason
Electrical engineer on his way to the installation.
Technical Capacity: 139,49 GWh/d Unavailable Capacity: 139,49 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped for unknown electrical reason
Electrical engineer on his way to the installation.
Technical Capacity: 144,00 GWh/d Unavailable Capacity: 144,00 GWh/d Available Capacity: 0,00 GWh/d
Issues with the compressor.
problems solved.
Technical Capacity: 144,00 GWh/d Unavailable Capacity: 144,00 GWh/d Available Capacity: 0,00 GWh/d
Issues with the compressor.
As of yet the exact cause is unknown, so the event stop time can shift.
Technical Capacity: 151,86 GWh/d Unavailable Capacity: 151,86 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped
reset takes approx 2 hours
Technical Capacity: 151,86 GWh/d Unavailable Capacity: 151,86 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped
reset takes approx 2 hours
Technical Capacity: 151,86 GWh/d Unavailable Capacity: 151,86 GWh/d Available Capacity: 0,00 GWh/d
Injection compressor has tripped
reset takes approx 2 hours
Technical Capacity: 151,86 KWh/d Unavailable Capacity: 6327656,00 KWh/d Available Capacity: 0,00 KWh/d
Injection compressor has tripped
reset takes approx 2 hours
Technical Capacity: 161,96 GWh/d Unavailable Capacity: 161,96 GWh/d Available Capacity: 0,00 GWh/d
Under investigation, compressor related.
Under investigation, compressor related.
Technical Capacity: 161,96 GWh/d Unavailable Capacity: 161,96 GWh/d Available Capacity: 0,00 GWh/d
Under investigation, compressor related.
Under investigation, compressor related.
Technical Capacity: 161,96 GWh/d Unavailable Capacity: 161,96 GWh/d Available Capacity: 0,00 GWh/d
Under investigation, compressor related.
Under investigation, compressor related.
Technical Capacity: 161,96 GWh/d Unavailable Capacity: 161,96 GWh/d Available Capacity: 0,00 GWh/d
Under investigation, compressor related.
Under investigation, compressor related.
Technical Capacity: 16,76 GWh/d Unavailable Capacity: 16,76 GWh/d Available Capacity: 0,00 GWh/d
Unavailable due to powerfail compressor
Startup compressor cylus estimated time one hour
Technical Capacity: 16,76 GWh/d Unavailable Capacity: 16,76 GWh/d Available Capacity: 0,00 GWh/d
Unavailable due to powerfail compressor
Startup compressor cylus estimated time one hour
Technical Capacity: 168,71 GWh/d Unavailable Capacity: 168,71 GWh/d Available Capacity: 0,00 GWh/d
Technical problem with compressor.
Issue has been solved.
Technical Capacity: 168,71 GWh/d Unavailable Capacity: 168,71 GWh/d Available Capacity: 0,00 GWh/d
Technical problem with compressor.
Technical Support is NOT on site yet, but has just been informed and travelling to the location.
Technical Capacity: 247,44 GWh/d Unavailable Capacity: 247,44 GWh/d Available Capacity: 0,00 GWh/d
Gas quality restrictions
Resolved
Technical Capacity: 191,20 GWh/d Unavailable Capacity: 191,20 GWh/d Available Capacity: 0,00 GWh/d
Gas quality restrictions.
Resolved.
Technical Capacity: 440,00 GWh/d Unavailable Capacity: 440,00 GWh/d Available Capacity: 0,00 GWh/d
Not given, this is a pre 01-01-17 message
Not given, this is a pre 01-01-17 message
Technical Capacity: 123,72 GWh/d Unavailable Capacity: 123,72 GWh/d Available Capacity: 0,00 GWh/d
Not given, this is a pre 01-01-17 message
Not given, this is a pre 01-01-17 message
Technical Capacity: 123,72 GWh/d Unavailable Capacity: 123,72 GWh/d Available Capacity: 0,00 GWh/d
Not given, this is a pre 01-01-17 message
Not given, this is a pre 01-01-17 message
Technical Capacity: 10,00 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 10,00 GWh/d
This UMM was placed unintentionally. Submitted by testing a new system connection (GIE).
This UMM was placed unintentionally. Submitted by testing a new system connection (GIE).
Technical Capacity: 10,00 GWh/d Unavailable Capacity: 0,00 GWh/d Available Capacity: 10,00 GWh/d
reason
remarks
Technical Capacity: 162,72 GWh/d Unavailable Capacity: 1,00 GWh/d Available Capacity: 161,72 GWh/d
Only for test purposes IT system, no actual unavailability for injection side GRK.
TEST COMPLETED
Technical Capacity: 162,72 GWh/d Unavailable Capacity: 1,00 GWh/d Available Capacity: 161,72 GWh/d
Only for test purposes IT system, no actual unavailability for injection side GRK.
TEST